Asbestos removal works

Asbestos imported from the 1970’s to the 1980’s have possibility been used widely in industrial furnaces constructed in these periods. The scope of use is backup materials of refractories inside furnaces, heat insulating materials surrounding ducts and pipes, packing for flanges, heat insulation materials for chimneys and flues, etc.

When repairing facilities which are used asbestos or demolitioning due to their deterioration, preventing workers’ health problems caused by asbestos based on “Ordinance on Prevention of Health Impairment due to Asbestos” is a responsibility of business operators.

We provide asbestos demolition works specialized in industrial furnaces and incidental facilities. Also, we investigate against possibility of asbestos contains and also perform selection and construction of alternative refractories after asbestos removal. Should you need any help for asbestos removal associated with industrial furnace repair and or facility demolition, please contact us by all means.

Please refer to our procedures for asbestos removal works, below.

The flow of asbestos removal works

  • Preliminary investigation(Sample collection and analysis)

    After collecting samples of refractories, they are analyzed by specialized company to investigate whether or not asbestos is contained, its concentration and the materials used.

  • Making construction planning sheet(Process consideration/ Plan creation)

    Based on the results of the preliminary survey and drawings of the demolish site, we plan demolition procedures and routes for transporting materials and equipment, and create a removal execution plan.

  • Notification to each government office(Labor Standards Inspection Office, Prefectural Bureau of Civil Affairs, etc.)

    Levels of demolition works of Asbestos differ depends on the contents. In connection with this, the contents and timing of submissions to each government offices differ. We make appropriate notification in accordance with the contents of the demolition.

  • On-site curing work

    On-site curing work

    We carry out curing of the site according to the construction plan. We create scaffolding and carry out on- site isolation and curing.

  • Asbestos removal work

    Asbestos removal work

    We dismantle refractory materials containing asbestos. In order to suppress the dispersion of asbestos, we moisten the work area while carry out works by spraying scattering inhibitor against asbestos dispersal.

  • Bagging waste asbestos

    Bagging waste asbestos

    We double-pack the removed asbestos into dedicated bags. After double-packing, we carry them out from the curing area and transport to a temporary storage area at the site.

  • Cleaning of curing area

    Cleaning of curing area

    Finishing and cleaning of detail parts and spraying with shattering inhibitor agent to stabilize.

  • Environmental measurement and curing removal

    Environmental measurement and curing removal

    After the removed material has been taken off-site, the asbestos concentration in the air at the site is measured. After confirming that the specified value has been achieved, we remove curing.

  • Transport and disposal of asbestos waste

    Transport and disposal of asbestos waste

    We will transport the asbestos waste to a licensed industrial waste disposal site for final disposal.

  • Submitting a work completion report to the Labor Standards Inspection Office & Prefectural Citizens Bureau

    We report various measurement values, work records, and work processes during the demolition work.

  • Install isolation sheets and other preliminary measures, including erecting scaffolding
    Install isolation sheets and other preliminary measures, including erecting scaffolding
    Removing the refractory materials containing asbestos
    Removing the refractory materials containing asbestos
    After the removal of asbestos
    After the removal of asbestos
    Double-bag the asbestos waste to package it
    Double-bag the asbestos waste to package it
    Carrying out and loading the asbestos waste
    Carrying out and loading the asbestos waste
    Wearing protective equipment
    Wearing protective equipments

Business Summary

We supply materials and technologies centered on fire resistance related to "Fire" and "Heat".

Osaka Taika Renga Co., Ltd. contributes to the industrial society by supplying materials and technologies and providing services centered on fire resistance related to "fire" and "heat".